Please find below the construction schedule for the next two weeks, March 2nd– 13th.

For your safety and that of our crews, please stay off active construction sites and old cart paths until they are reopened.

 

Scheduled Work:

  • 2nd -6th: Weather Permitting:
    • Beemer to be testing all water/sewer/storm lines on 1st plat by the end of the week.
    • Sosaya to begin boring for electric lines under the roads to connect plats 1, 3 and 4 at the end of the week.
    • Rock and dirt moved to create berms, these may be crossing plats as needed.
  • 9th-13th:
    • Sosaya to finish any boring remaining. Upon completion of boring, Evergy will be scheduled to come and make electrical connections.
    • Rock and dirt moved to create berms, these may be crossing plats as needed.

 

Expected Impacts:

  • Electric line boring and potholing, as needed.
  • Walking paths of holes 1-9 closed, expected to reopen in Summer of 2026.
  • Road plate across Grace Dr., connecting holes 4 and 5, expected to stay until Fall of 2026 to protect road.
  • Construction Hours: Monday – Friday 7am- 6pm, Saturdays as needed 8am -3pm